Great Panther Silver Reports Production Results

 

VANCOUVER, BC - Great Panther reported second quarter (Q2) production results at its two wholly-owned Mexican silver mining operations, Guanajuato and Topia, and provided an update on its exploration and development activities.

Great Panther delivered continued growth in metal production during the second quarter of 2014. Production in terms of Ag eq oz increased 6% compared to the second quarter of 2013 and showed an 8% increase over the first quarter of 2014. This was primarily due to increased mill throughput at both mines combined with better silver grades from the Guanajuato Mine Complex over the first quarter as operations fully resumed after the disruptions in the first quarter. At Guanajuato, the start of commercial production at San Ignacio in June and the provision of pre-production development ore contributed to the increased throughput and metal production.

"We saw a steady improvement at Guanajuato through the quarter and were very pleased to initiate commercial production on schedule at San Ignacio, a new satellite operation of Guanajuato," stated Robert Archer, President and CEO. "We anticipate that production growth will continue, especially as we ramp up production at San Ignacio."

Ore processed at Guanajuato increased 20% and 15%, to a record 63,646 tones, compared to the same period in 2013 and the first quarter of 2014, respectively. This resulted in a 1% and 15% increase in metal production for the comparative period last year and the first quarter of 2014, respectively. Metal production for the second quarter of 2014 included 251,687 Ag oz and 3,648 Au oz, or 470,589 Ag eq oz at grades of 139 grams per tone (g/t) Ag and 1.99g/t Au.

Ore processed at Guanajuato came primarily from the Cata mine followed by the Santa Margarita, Los Pozos and Guanajuatito mines. Production growth from the Cata mine was achieved through synchronized exploitation of the hanging wall veins (Alto 1, 2 & 4), Contact vein, and the main Veta Madre vein from the upper 390 meter level to the 540 meter level. The gradual increase of mill feed from San Ignacio also contributed to overall production volumes, accounting for a total of 12,880 tones in the second quarter.

Both silver and gold grades decreased over the corresponding period in 2013, however, silver grades improved 9% over the first quarter of 2014. Gold grades were slightly below those of the previous quarter as work at the gold-rich Santa Margarita mine focused on the development of new production levels.

The plant delivered metal recoveries of 88.4% for silver and 89.4% for gold. Silver recoveries improved slightly compared to the same quarter last year and the first quarter of this year due to modifications in the flotation circuit, however, gold recoveries declined due to the processing of lower gold grade ore.

The second quarter of 2014 saw less exploration drilling at Guanajuato compared to both the same period in 2013 and the previous quarter due to a greater focus on the preparation of underground infrastructure for future drilling. The majority of the diamond drilling during the quarter was undertaken at the Cata mine, exploring the hanging wall veins system (Altos) from the 490 to the 540 meter level. In addition, extension and infill drilling was conducted at the upper levels of Santa Margarita between the 345 and 275 meter levels. This provided encouraging intersections of the Veta Madre and Santa Margarita veins, including two intermediate mineralized structures. The drilling program for the second half of 2014 is composed of infill and extension drilling primarily at the deep Cata and Santa Margarita mines.

Underground development at Guanajuato was up 34% and 27% compared to the same period in 2013 and the first quarter of 2014, respectively. Encouraging drill intercepts were revealed in the primary Veta Madre vein at the 540 meter level of the Cata mine. Further development was conducted to explore and define the continuity of the Alto 4 and Alto 2 veins at the 465 meter and 490 meter level, respectively. The Guanajuatito mine access ramp reached the 285 meter level and the vein was successfully intersected by crosscutting leading to the initiation of mining on this level subsequent to the end of the quarter.

San Ignacio Mine

As noted, San Ignacio commenced commercial production in June and contributed 12,880 tones of mill feed for the second quarter. This represented a 60% increase compared to the first quarter of 2014 during which development ore only was processed. Metal production from San Ignacio was 87,705 Ag eq oz, which included 35,294 Ag oz and 873 Au oz, or 87,705 Ag eq oz at ore grades of 104g/t Ag and 2.55g/t Au. The gradual increase of pre-production mill feed followed by the commencement of stope production contributed to the Company's overall production and is included under the Guanajuato Mine Complex. The mine is currently operating at a run rate of approximately 200 tones per day and will increase gradually as new stopes are brought into production.

Early in the second quarter, pre-production operations at San Ignacio focused primarily on the 2300 meter level (above mean sea level), developing access drifts and preparing stopes on the Intermediate vein and, to a lesser degree, on the Melladito vein. Exploration cross-cuts revealed well mineralized vein material that was subsequently mined. Stopping commenced later in the quarter on the 2300, 2320 and 2317 meter levels. The mine ventilation system was upgraded with a ventilation raise connecting the 2317 meter level to the surface.

The ramp has reached the 2280 meter level where the Company is developing a new production level and stopes on both the Intermediate and Melladito veins. The access ramp is anticipated to reach the 2250 meter level by the end of the third quarter.

Ancillary surface infrastructure at San Ignacio was further improved by the completion of the mechanical services workshop. This is expected to reduce equipment maintenance times and increase mechanical availabilities. The mine portal patio was expanded to facilitate the transition of personnel and equipment in and out of the mine and an additional air compressor was installed to support the existing line.

Topia Mine

Ore processed at Topia increased 18% to 17,319 tones when compared to the corresponding quarter in 2013, and remained steady when compared to the first quarter of 2014. Total metal production increased 16% over the same quarter in 2013 but decreased slightly over the first quarter of this year. Metal production for the second quarter included 168,314 Ag oz, 125 Au oz, 302 lead (Pb) tones and 395 zinc (Zn) tones, or 248,205 Ag eq oz. Ore grades were 336g/t Ag, 0.40g/t Au, 1.84% Pb and 2.49% Zn. Silver grades were down somewhat from the same quarter the previous year but only slightly down from the first quarter of this year.

Ore processed at Topia came primarily from the Argentina, Durangueno and 15-22 mines, which accounted for approximately 50% of throughput. The lower ore grades for the second quarter can be attributed to higher dilution and mining from zones under development. The reduction of dilution is an ongoing priority in order to increase ore grades at Topia. Furthermore, each mine is continually assessed as to its individual economic viability and, at the end of June, the Oliva Mine was shut down. Men and equipment have redeployed elsewhere so as to have no impact on production.

Metal recoveries were down slightly when compared to the same quarter in 2013, at 89.8% for silver, 56.1% for gold, 94.7% for lead and 91.6% for zinc. However, these recoveries were an improvement over the first quarter of this year due to process optimization measures implemented earlier this year on the crushing and flotation circuits of the plant.

As anticipated, exploration development at the Durangueno and San Gregorio mines intersected the Rosario vein and development was carried out to prepare sublevels, raises and stopes for production.

Underground development was up 20% and 36%, to 2,708 meters, compared to the same period in 2013 and the first quarter of 2014, respectively, as a result of a new development program focused on extending access ramps and drifts to new mineralized zones.

At this time, plans for El Horcon are limited to applying for the necessary government permits to allow further exploration and development. This project has the potential to be another satellite mine to the Company's Guanajuato operation, leveraging excess capacity at its Cata processing plant.

Outlook

The Company is maintaining its 10% production growth guidance for 2014 and cash costs are expected to improve as we progress throughout the year. However, due to the focus on San Ignacio development and efforts to normalize operations at Guanajuato from the disruptions in the first quarter, we are reviewing our cost guidance and will provide a further update with the Q2 earnings release.

Exploration drilling at Guanajuato will focus on upgrading mineral resource estimates at Valenciana, Cata, San Cayetano, Guanajuatito and Los Pozos before the end of the year.